Project update

PUERTO DE LA TORRE IV

September 07, 2022

Update from the originator: 

As you know, this process, of all the projects that are in recovery, was left under the supervision of the company and is expected to last about 24 months, so until then, the originator may not have much information. Please note that, once a debt is transferred to a recovery agency, legally, the intermediary or the person who has transferred the debt to a recovery company has no authority to interfere in the negotiations that the recovery agency and the debtor carry out, nor in the speed at which these are presented, but it is the recovery agency that carries out the relevant timing. As soon as the recovery agency provides the originator with any kind of update, no matter how small, we will send it to you immediately by means of communication on the timeline.


March 11, 2022

Update from the originator:

The debt collection procedure has already started. This type of procedure is related to the monitoring and execution of the guarantees offered.

The originator informs you that this is a procedure that whenever there are advances, or updates will be communicated to the intervening investors, however, it is a procedure that should not exceed the maximum period of 2 years.


February 10, 2022

Update from the originator:

The originator informs you that the ordinary lawsuit has been filed against the developer of the project "Puerto de la Torre IV" to claim the amount owed by the developer. In this way, legal action has already been taken to recover the loan, as agreed at the investors' meeting held for this purpose. As soon as the originator has news about the admission and distribution of the lawsuit, the originator will inform you.


June 28, 2021

Update from the originator:

New documents have been added to the documents section.


May 25, 2021

Update from the originator:

A new document has been released and added to the "documents" section.


April 09, 2021

Update from the originator:

The originator would like to inform you that the originator is following up on this situation, however, the originator informs you that no transfer has yet been made by the promoter, and the originator has already contacted them and so far no response has come from them.


February 11, 2021

Update from the originator:

The originator is stating that the promoting company has already been contacted in order to understand why it is not carrying out the distribution of income interest as well as the procedure to be carried out in order to regularize this situation, however, in the originator's opinion it is a punctual delay in the distribution of income interest. 


February 03, 2021

Update from the originator:

To match the return date of all the tranches of the project, the promoter has requested a restructuring of the payment schedule. The originator is analyzing the viability of the proposed plan before a meeting of lenders for approval is set.