Update from the originator:
A new document regarding the project's progress has been added to the document section.
Update from the developer:
The construction company is laying the aluminum carpentry and parquet. Currently, 80% of services have been executed.
Forecast to finish: May 2021, according to the planned schedule.
A new document, containing the pictures of the progress has been attached.
Update from the originator:
Due to the good acceptance of the project " Edifici Pi i Maragall - Stage II " the project was extended by 25% of the amount to be financed (as provided in the contract).